1.
(1)施工合同对工期相关要求。
(2)批准的设计文件。
(3)通信工程各专业施工工序之间的工艺关系及施工定额。
(4)通信工程建设相关法律法规、公司的相关管理制度和管理程序。
(5)现场摸底报告,或者已经掌握的施工现场具体环境条件。
(6)拟投入项目的人员、工器具仪表设备数量,材料和设备供应条件。
(7)以往类似工程的实际进度及经济指标。
2.BCWS=(1x500x7+2x500x7)(第一周)+(2x500x7+5x500x7+1x500x7+4x500x7)(第二周)+( 2x500x7+5x500x7+1x500x7+4x500x7) ( 第三周) +( 2x500x7+5x500x7+1x500x7+4x500x7) ( 第四周) +(1x500x7+4x500x7+1x500x7+2x500x7+1x1000x7)(第五周)+(1x500x7+2x500x7+1x1000x7)(第六周)=189000元
BCWP=(1x500x7+2x500x7)(机房测量)+(2x500x7+5x500x7)(A 线走线架安装)+(1x500x7+4x500x7)x2(B 站走线架安装)+(2x500x7+5x500x7)x2(A 站设备安装)+(1x500x7+4x500x7)x2(B 站设备安装)+
(1x500x7+2x500x7+1000x7)(A 站测试)+(1x500x4+2x500x4+1000x4)(B 站测试)=181500 元
ACWP=1x500x7+2x500x7+2x500x7+5x500x7+1x500x7+4x500x7+2x500x7+5x500x7+2x500x7+5x500x7+1x500x7+4x500x7+(2+1+5+4)x3x100+1x500x7+4x500x7+1x500x7+4x500x7+(1+4)x100x2+1x500x7+2x500x7+1000x7+1000x3+1x500x4+2x500x4+1000x4=189100 元
3.CV=BCWP-ACWP=181500-187900=-6400
SV=BCWP-BCWS=181500-189000=-7500
因为BCWS>ACWP>BCWP,SV<0,CV<0,所以进度较慢,效率低,应采取的措施是迅速增加高效人员的投入
4.本工程的实际费用:
ACWP=【1x500x7+2x500x7+2x500x7+5x500x7+1x500x7+4x500x7+2x500x7+5x500x7+2x500x7+5x500x7+1x500x7+4x500x7+(2+1+5+4)x3x100+1x500x7+4x500x7+1x500x7+4x500x7+(1+4)x100x2+1x500x7+2x500x7+1000x7+1000x3+1x500x4+2x500x4+1000x4】(前九周的ACWP)+(1x500x3x2x500x3x1000x3)(A 站设备测试后来完成的费用)+(1x500x7+2x500x7+1000x7)( B 站单机测试) + ( 1x500x7+2x500x7+1000x7 ) ( B 站系统测试)+1x500x4+2x500x4+1x500x4+2x500x4+1x500x1+2x500x1=249600 元
第九周末时竣工验收只完成了4+4x1/2=6 天的量,而竣工验收是七天完成,所以第九周末工程未完成。
5.本工程的开工日期是8.28,所以质量监督的申报时间是开工日期前的五个工作日前,所以质量监督的申报时间为:8.23 日以前。
本工程的竣工验收时间是10.31.日,竣工验收备案的时间是竣工验收合格之日内的15 日内,所以竣工验收备案的时间为10.31 到11.15 日内。
本工程未说明质量保修期,所以质量保修期按12 个月算,质量保修金的结算时间次年的10.31 后进行结算。
6.机架和子架安装检查:机架安装平面位置;机架垂直、水平度;机架上下加固;机架接地线;机架附件的放置;子架安装位置;子架内机盘的安装;子架内缆、线、纤的固定;子架附件的放置。